Help Us Beautify Geary – and Learn the Latest on the Corridor’s Transit and Safety Upgrades

Help Us Beautify Geary – and Learn the Latest on the Corridor’s Transit and Safety Upgrades
By David Sindel

A 38 Geary bus heads east on Geary Boulevard, passing 21st Ave. in a designated transit lane. Cars follow in adjacent lanes.A 38 Geary bus beats traffic in the new transit lanes installed last fall.

The Geary Boulevard Improvement Project aims to address bus delays and traffic concerns on a high-injury corridor. Community feedback played a major role in the transit and safety improvements we’re bringing to Geary. 

As we share the latest on these upgrades, we invite you to weigh in on a new topic: beautification. 

Join us Wednesday, April 17 for an open house about community enhancement for the Geary Boulevard Improvement Project.  

Date/time: Wednesday, April 17, 2024 from 5 - 7 p.m. 

Location: Presidio Middle School Library – 450 30th Avenue, 2nd floor 

Selecting the best option to beautify Geary 

At the open house, drop in to learn more about seven options to beautify Geary Boulevard. They include:  

  • Sidewalk pavers 

  • Etched/stamped sidewalk concrete 

  • Decorative sidewalk concrete with glass aggregate 

  • Street trees 

  • Leaning rails at bus stops 

  • Large district marker 

  • Small neighborhood identity markers 

You can see examples and more information on our Geary Boulevard Improvement Project Community Enhancement webpage

Some of these options provide the opportunity to highlight the Richmond District’s rich history and/or culture. Others contribute to neighborhood identity or place-making. For example, decorative sidewalk designs at bus stops could highlight local culture. Or, a large district marker could pay homage to the surrounding architectural styles. New street trees could spruce up the boulevard. Sidewalk pavers could add to its character. 

Photo on left shows an example of a district marker; upper right shows etched concrete; lower right a concrete and glass treatment
Photo on left shows an example of a district marker; upper right shows etched concrete; lower right a concrete and glass treatment.

Welcoming feedback online or in person 

You can take the Geary Boulevard Improvement Project Community Enhancement Survey now.

You can also attend the open house on April 17 to learn more, chat with staff and submit your survey in person. We look forward to your feedback! 

We will have a second round of outreach later this year. At that time, we’ll share the favorite treatment(s) and ask for feedback on the details of the design. Crews will install the selected treatment during the construction phase of the project. This stage includes other planned utility, transit, safety and pavement improvements. 

People board a 38R bus at Park Presidio and Geary. We see a bus shelter with an ad on it and Park Presidio on a green sign above the bus.

People board at a Geary 38 stop that was relocated to help improve travel times.

Improving bus travel times with Quick-Build work 

As we welcome new ideas for beautification, we’re proud to share an early win for the corridor. 

We recently completed implementation of the “Quick-Build” phase, which included new transit lanes between 15th and 28th avenues. It also included bus stop changes to improve reliability of Muni’s 38 Geary line and safety treatments. Preliminary results already show improved bus travel times for over 40,000 daily riders. Muni operators say the changes are helping. We plan to publish a full evaluation report later this year.

Finding creative ways to support businesses 

We also devoted project funding to support local businesses. Our goal: find creative ways to attract customers to the corridor. 

To make this happen, we're convening a Geary Small Business Working Group. Our project team is working to execute the group's priorities: 

  • Wrap Geary Boulevard tree trunks with decorative lighting 

  • Create an ad campaign on Muni buses to promote the Central Richmond 

Infographic shows timeline for Geary Boulevard Improvement Project updates.

Preparing for the next steps: utility upgrades, then transit and safety work 

Starting in early 2025, SFPUC will begin upgrading the sewer and water lines along Geary. For more information, you can visit the SFPUC’s Geary Boulevard Sewer and Water Improvements project webpage. 

Additional transit and safety improvements will begin in 2026. During this stage, we will install the selected community enhancement. 

This construction phase will also include: 

  • Bulb-outs to expand passenger waiting areas 

  • Pedestrian bulb-outs and median refuges to make crossing Geary Boulevard safer 

  • Upgrades of aging traffic signals 

After the entire project corridor is freshly repaved, crews will also paint transit lanes red. 

You can learn more about the project and subscribe for updates by visiting the Geary Boulevard Improvement Project page (SFMTA.com/Geary). 



Published April 16, 2024 at 03:07AM
https://ift.tt/c0jAr8s

Comments

Popular posts from this blog

Help Make Muni Safe for Everyone

Help Make Muni Safe for Everyone By Mariana Maguire New Muni “no harassment” symbol The safety of our customers and staff is a top priority for the SFMTA. That is why we are launching MuniSafe – a campaign to increase reporting of gender-based harassment through recently expanded incident reporting options. If you experience or witness an incident, help us make MuniSafe by reporting it using the Muni Feedback form at SFMTA.com/MuniFeedback, the 311 mobile app or by calling 311. Non-English speakers should call 311 for language-assisted reporting. Gender-based harassment takes many forms, affects many people and is absolutely not tolerated on Muni. Survivors should report incidents to the San Francisco Police Department if they feel comfortable doing so. By also reporting incidents directly to the SFMTA, you will help us track events that occur in our system so we can build better safety responses and direct resources to reduce gender-based harassment. New car cards that will be...

L Taraval Improvement Project “Segment B” Geared Up for Early 2022

L Taraval Improvement Project “Segment B” Geared Up for Early 2022 By Stephen Chun Over the summer, we shared the good news that the  first segment  of the  L Taraval Improvement Project  was  completed on schedule and within budget.  A notice to proceed for the next phase of work, Segment B was issued last week to NTK Construction. Project staff is now gearing up for work slated to begin in January 2022.   What is the L Taraval Improvement Project?  The L Taraval Improvement Project is a multi-agency collaboration partnered with the San Francisco Public Utilities Commission and the Department of Public Works to improve and upgrade the aging infrastructure. The project will make pedestrian crossing safer, increase accessibility, improve transit reliability, rehabilitate water and sewer infrastructure, enhance landscaping and replace road pavement along the L Taraval line....

Do exercise to keep fit

Health is wealth